Updated Nov 2026 | Lien Waivers: 25 Del. C. § 2706
Delaware is one of the more protective states for subcontractors, sub-subs, and suppliers on private projects. The statute shuts down most attempts to strip mechanics lien rights in advance. Those protections still have limits: a waiver signed at the wrong moment, or one that says more than it should, can cost you payment. Here’s how the rules work and what to check before you sign.
Advance Waivers Are Void
Under 25 Del. C. § 2706(b), any contract, agreement, or understanding that waives your right to file or enforce a mechanics lien is void as against public policy. That includes waiver language in your subcontract. A waiver you sign before you’re paid has no effect.
The statute allows only two kinds of waiver:
- A written waiver signed and delivered upon or after payment. It waives the right to lien only for the labor or materials a specific payment was for.
- A written agreement to subordinate, release, or satisfy a lien after a lien is filed, e.g. upon final payment.
Delaware has no statutory waiver form, so the wording of each waiver must be closely examined to avoid unwittingly releasing rights to unpaid work or deliveries.
What to Check Before You Sign
Confirm the funds have cleared. A waiver delivered against a check that later bounces may release a lien that may still need to be filed and enforced. Exchange the waiver for cleared funds.
Match the amount. The waiver should reflect what you actually receive, not the contract total or your billed amount.
Limit the scope. Tie the waiver to a specific “through” date. Clarify what is excluded: retainage, pending change orders, claims, and extras.
Hold the final release. Sign a final release only with the final full payment, including retainage.
Read past the waiver language. Critical especially if the waiver was supplied by the hiring party for you to sign. Make sure to strike any overreaching language, “no further claims”, or bond-claim releases that go beyond the payment in hand.
Credit and Notes Don’t Waive Your Lien
Under § 2706(a), extending credit or accepting a promissory note or other security doesn’t waive your lien. It only suspends your lien rights until the agreed credit period ends. The exceptions are if claimants explicitly accept the note as payment or expressly waive the lien. Be wary of signing anything that states that credit satisfies a debt or constitutes as payment that clears your right to lien.
Owner-occupied Residences
Section 2707 applies when the property is used solely as the owner’s residence. On those jobs, if the owner makes full or final payment to the GC in good faith, no lien attaches, even if you were never paid.
Before or at final payment, the GC must give the owner one of two documents:
- a notarized, verified certification that everyone has been paid, or
- a release signed by every sub and supplier.
If you sign that release before you’re paid and the owner pays the GC in reliance on it, your lien is gone.
If the owner hasn’t paid in full, your lien is limited to the unpaid balance. That balance is shared pro rata among the claimants who perfect liens. Once the writ of scire facias is served under § 2715, the owner’s later payments to the GC no longer count as “in good faith,” which protects the remaining balance.
The Owner Can Demand a List of Claimants
Under § 2705, an owner can demand a written list of everyone who furnished labor or materials. A contractor or sub that doesn’t provide it within 10 days loses its lien rights and receives no further payment until it does. If you have your own sub-tiers, keep that list current.
Waiver Negotiations Don’t Stop the Clock
Your statement of claim is due within 120 days of your last labor or delivery. Section 2711(b) also treats a claim as timely if it’s filed within 120 days of either of these dates:
- the date your final payment, including retainage, is due, or
- the date the prime contractor receives final payment.
Don’t plan around those alternatives. Calendar 120 days from last furnishing. Negotiating waivers or a payment plan doesn’t extend the deadline. File first, then settle with a post-filing release under § 2706(b).
Based on 25 Del. C. §§ 2705–2707, 2711, and 2715. Have counsel review any disputed or unusual waiver form.